How to Calculate Float (A/K/A Slack)
Float (A/K/A Slack) Float = Late Start (LS) – Early Start (ES) Float = Late Finish (LF) – Early Finish (EF) %3D Float is the amount of time án activity cạn be delayed. without delaying the project end dațe. There are two ways to calculate it using the critical path method. Both 'ways are set forth above. When calculating float, know that zero (0) float means that if one. delay occurs, the project will fall behind- .schedule. Remember that the activities on the critical path (critical activities) have a float of zero. MYPM МyРМ .....
How to Calculate Float (A/K/A Slack)
shared by MyPM on Apr 27
23
views
0
faves
0
comments
This is the project management formula used for calculating float.